Holland, Michigan, Will Expand Pilot To More Of Downtown

In January 2016, Holland, Michigan, made commencing fiber-optic Internet access to residential neighborhoods its number one goal for fiscal year 2017. They’re a little behind schedule, but the town is now moving forward by expanding a pilot project in order to serve a larger downtown area.

It's Really Happening

The Holland Board of Public Works (BPW) held an informational meeting on March 13th to answer questions from the community and share plans for the potential expansion. About a year ago, we reported on the results of a study commissioned by the city in which, based on a take rate of about 40 percent, 1 Gigabit per second (1,000 Mbps) connectivity would cost residents about $80 per month. Small businesses would pay approximately $85 per month and larger commercial subscriber rates would run around $220 per month. The update on the plan confirms those figures, noting that the four businesses that tested the pilot services had positive experiences. As a result, BPW feels it’s time to expand to more of downtown.

"If it goes really well we hope to be able to expand the service out as far into the community as we can," said Pete Hoffswell, broadband services manager at BPW.

The expansion is planned for construction in June and July, with service testing in August. Actual delivery would be in September, BPW estimates.

BPW will use a boring technique to place conduit and fiber below ground so there will be minimal disruption. No streets will be closed. Next, BPW will get construction bids, evaluate them, and present them to the City Council for approval.

Not An Impulse Decision

tulips.jpeg Holland has had dark fiber in place for decades for the municipal electric operations. Later BPW extended it to schools and businesses that needed high capacity data services. After years of incremental expansions, the network is now more than 150 fiber miles throughout the city.

Holland, Michigan, Will Expand Pilot To More Of Downtown

In January 2016, Holland, Michigan, made commencing fiber-optic Internet access to residential neighborhoods its number one goal for fiscal year 2017. They’re a little behind schedule, but the town is now moving forward by expanding a pilot project in order to serve a larger downtown area.

It's Really Happening

The Holland Board of Public Works (BPW) held an informational meeting on March 13th to answer questions from the community and share plans for the potential expansion. About a year ago, we reported on the results of a study commissioned by the city in which, based on a take rate of about 40 percent, 1 Gigabit per second (1,000 Mbps) connectivity would cost residents about $80 per month. Small businesses would pay approximately $85 per month and larger commercial subscriber rates would run around $220 per month. The update on the plan confirms those figures, noting that the four businesses that tested the pilot services had positive experiences. As a result, BPW feels it’s time to expand to more of downtown.

"If it goes really well we hope to be able to expand the service out as far into the community as we can," said Pete Hoffswell, broadband services manager at BPW.

The expansion is planned for construction in June and July, with service testing in August. Actual delivery would be in September, BPW estimates.

BPW will use a boring technique to place conduit and fiber below ground so there will be minimal disruption. No streets will be closed. Next, BPW will get construction bids, evaluate them, and present them to the City Council for approval.

Not An Impulse Decision

tulips.jpeg Holland has had dark fiber in place for decades for the municipal electric operations. Later BPW extended it to schools and businesses that needed high capacity data services. After years of incremental expansions, the network is now more than 150 fiber miles throughout the city.

Holland, Michigan, Will Expand Pilot To More Of Downtown

In January 2016, Holland, Michigan, made commencing fiber-optic Internet access to residential neighborhoods its number one goal for fiscal year 2017. They’re a little behind schedule, but the town is now moving forward by expanding a pilot project in order to serve a larger downtown area.

It's Really Happening

The Holland Board of Public Works (BPW) held an informational meeting on March 13th to answer questions from the community and share plans for the potential expansion. About a year ago, we reported on the results of a study commissioned by the city in which, based on a take rate of about 40 percent, 1 Gigabit per second (1,000 Mbps) connectivity would cost residents about $80 per month. Small businesses would pay approximately $85 per month and larger commercial subscriber rates would run around $220 per month. The update on the plan confirms those figures, noting that the four businesses that tested the pilot services had positive experiences. As a result, BPW feels it’s time to expand to more of downtown.

"If it goes really well we hope to be able to expand the service out as far into the community as we can," said Pete Hoffswell, broadband services manager at BPW.

The expansion is planned for construction in June and July, with service testing in August. Actual delivery would be in September, BPW estimates.

BPW will use a boring technique to place conduit and fiber below ground so there will be minimal disruption. No streets will be closed. Next, BPW will get construction bids, evaluate them, and present them to the City Council for approval.

Not An Impulse Decision

tulips.jpeg Holland has had dark fiber in place for decades for the municipal electric operations. Later BPW extended it to schools and businesses that needed high capacity data services. After years of incremental expansions, the network is now more than 150 fiber miles throughout the city.

Holland, Michigan, Will Expand Pilot To More Of Downtown

In January 2016, Holland, Michigan, made commencing fiber-optic Internet access to residential neighborhoods its number one goal for fiscal year 2017. They’re a little behind schedule, but the town is now moving forward by expanding a pilot project in order to serve a larger downtown area.

It's Really Happening

The Holland Board of Public Works (BPW) held an informational meeting on March 13th to answer questions from the community and share plans for the potential expansion. About a year ago, we reported on the results of a study commissioned by the city in which, based on a take rate of about 40 percent, 1 Gigabit per second (1,000 Mbps) connectivity would cost residents about $80 per month. Small businesses would pay approximately $85 per month and larger commercial subscriber rates would run around $220 per month. The update on the plan confirms those figures, noting that the four businesses that tested the pilot services had positive experiences. As a result, BPW feels it’s time to expand to more of downtown.

"If it goes really well we hope to be able to expand the service out as far into the community as we can," said Pete Hoffswell, broadband services manager at BPW.

The expansion is planned for construction in June and July, with service testing in August. Actual delivery would be in September, BPW estimates.

BPW will use a boring technique to place conduit and fiber below ground so there will be minimal disruption. No streets will be closed. Next, BPW will get construction bids, evaluate them, and present them to the City Council for approval.

Not An Impulse Decision

tulips.jpeg Holland has had dark fiber in place for decades for the municipal electric operations. Later BPW extended it to schools and businesses that needed high capacity data services. After years of incremental expansions, the network is now more than 150 fiber miles throughout the city.

Businesses Selected For Ellensburg Pilot

Out of 58 business applications, the city of Ellensburg, Washington, recently selected 30 local businesses to participate in their fiber-optic pilot project. Nineteen participants are business owners, 11 are business tenants; 22 are located at commercial locations and six are home-based businesses along with two telecommuters, reports the Daily Record.

The participants will obtain a credit of $5,000 to connect to the network from the city’s telecommunications utility. Any connection fees over and above the credit will be the responsibility of the pilot project participants.

Businesses will be able to purchase Internet access from the city at either 300 Megabits per second (Mbps) capacity or gigabit (1,000 Mbps) capacity. Service is symmetrical, which is critical for business, so speeds are just as fast on the upload as on the download. Month service fees will be $39.95 and $59.95 per month respectively. The city expects to begin connecting businesses in August.

Businesses Selected For Ellensburg Pilot

Out of 58 business applications, the city of Ellensburg, Washington, recently selected 30 local businesses to participate in their fiber-optic pilot project. Nineteen participants are business owners, 11 are business tenants; 22 are located at commercial locations and six are home-based businesses along with two telecommuters, reports the Daily Record.

The participants will obtain a credit of $5,000 to connect to the network from the city’s telecommunications utility. Any connection fees over and above the credit will be the responsibility of the pilot project participants.

Businesses will be able to purchase Internet access from the city at either 300 Megabits per second (Mbps) capacity or gigabit (1,000 Mbps) capacity. Service is symmetrical, which is critical for business, so speeds are just as fast on the upload as on the download. Month service fees will be $39.95 and $59.95 per month respectively. The city expects to begin connecting businesses in August.

Businesses Selected For Ellensburg Pilot

Out of 58 business applications, the city of Ellensburg, Washington, recently selected 30 local businesses to participate in their fiber-optic pilot project. Nineteen participants are business owners, 11 are business tenants; 22 are located at commercial locations and six are home-based businesses along with two telecommuters, reports the Daily Record.

The participants will obtain a credit of $5,000 to connect to the network from the city’s telecommunications utility. Any connection fees over and above the credit will be the responsibility of the pilot project participants.

Businesses will be able to purchase Internet access from the city at either 300 Megabits per second (Mbps) capacity or gigabit (1,000 Mbps) capacity. Service is symmetrical, which is critical for business, so speeds are just as fast on the upload as on the download. Month service fees will be $39.95 and $59.95 per month respectively. The city expects to begin connecting businesses in August.

Businesses Selected For Ellensburg Pilot

Out of 58 business applications, the city of Ellensburg, Washington, recently selected 30 local businesses to participate in their fiber-optic pilot project. Nineteen participants are business owners, 11 are business tenants; 22 are located at commercial locations and six are home-based businesses along with two telecommuters, reports the Daily Record.

The participants will obtain a credit of $5,000 to connect to the network from the city’s telecommunications utility. Any connection fees over and above the credit will be the responsibility of the pilot project participants.

Businesses will be able to purchase Internet access from the city at either 300 Megabits per second (Mbps) capacity or gigabit (1,000 Mbps) capacity. Service is symmetrical, which is critical for business, so speeds are just as fast on the upload as on the download. Month service fees will be $39.95 and $59.95 per month respectively. The city expects to begin connecting businesses in August.

Businesses Selected For Ellensburg Pilot

Out of 58 business applications, the city of Ellensburg, Washington, recently selected 30 local businesses to participate in their fiber-optic pilot project. Nineteen participants are business owners, 11 are business tenants; 22 are located at commercial locations and six are home-based businesses along with two telecommuters, reports the Daily Record.

The participants will obtain a credit of $5,000 to connect to the network from the city’s telecommunications utility. Any connection fees over and above the credit will be the responsibility of the pilot project participants.

Businesses will be able to purchase Internet access from the city at either 300 Megabits per second (Mbps) capacity or gigabit (1,000 Mbps) capacity. Service is symmetrical, which is critical for business, so speeds are just as fast on the upload as on the download. Month service fees will be $39.95 and $59.95 per month respectively. The city expects to begin connecting businesses in August.

Businesses Selected For Ellensburg Pilot

Out of 58 business applications, the city of Ellensburg, Washington, recently selected 30 local businesses to participate in their fiber-optic pilot project. Nineteen participants are business owners, 11 are business tenants; 22 are located at commercial locations and six are home-based businesses along with two telecommuters, reports the Daily Record.

The participants will obtain a credit of $5,000 to connect to the network from the city’s telecommunications utility. Any connection fees over and above the credit will be the responsibility of the pilot project participants.

Businesses will be able to purchase Internet access from the city at either 300 Megabits per second (Mbps) capacity or gigabit (1,000 Mbps) capacity. Service is symmetrical, which is critical for business, so speeds are just as fast on the upload as on the download. Month service fees will be $39.95 and $59.95 per month respectively. The city expects to begin connecting businesses in August.