Requests for Proposals

Content tagged with "Requests for Proposals"

Displaying 631 - 640 of 955

Hudson, Ohio, Issues RFP for FTTH Study

Hudson is bringing better connectivity to local businesses with Velocity Broadband, its gigabit fiber network, and is now exploring the potential of Fiber-to-the-Home (FTTH) for the rest of the community. The city recently issued a Request for Proposals (RFP) for a feasibility study to review the possibilities for service to residents. Proposals are due August 26.

From the RFP Summary:

This project will result in the production of a Feasibility Study containing a residential needs assessment, deployment strategy options and construction cost estimates. The desired outcome of this planning effort is to provide a tool for the city to establish if Hudson residents want this service and determine a successful deployment strategy and the associated cost to implement fiber to the homes (FTTH) within the City of Hudson. 

The city wants the study completed by the end of 2016.

We’ve covered Hudson’s venture into accelerating connectivity for businesses since 2014. The community of 23,000 started by incrementally building out a fiber-optic institutional network (I-Net) over a period of about ten years, which it later expanded to offer gigabit service to businesses. Chris interviewed Hudson City Manager Jane Howington last December about the city’s Velocity service. Check out episode #181 of the Community Broadband Bits podcast for that conversation. Since the launch, local businesses have been excited to obtain fast, affordable, reliable connectivity.

The full RFP is available on the city's website.

Hudson, Ohio, Issues RFP for FTTH Study

Hudson is bringing better connectivity to local businesses with Velocity Broadband, its gigabit fiber network, and is now exploring the potential of Fiber-to-the-Home (FTTH) for the rest of the community. The city recently issued a Request for Proposals (RFP) for a feasibility study to review the possibilities for service to residents. Proposals are due August 26.

From the RFP Summary:

This project will result in the production of a Feasibility Study containing a residential needs assessment, deployment strategy options and construction cost estimates. The desired outcome of this planning effort is to provide a tool for the city to establish if Hudson residents want this service and determine a successful deployment strategy and the associated cost to implement fiber to the homes (FTTH) within the City of Hudson. 

The city wants the study completed by the end of 2016.

We’ve covered Hudson’s venture into accelerating connectivity for businesses since 2014. The community of 23,000 started by incrementally building out a fiber-optic institutional network (I-Net) over a period of about ten years, which it later expanded to offer gigabit service to businesses. Chris interviewed Hudson City Manager Jane Howington last December about the city’s Velocity service. Check out episode #181 of the Community Broadband Bits podcast for that conversation. Since the launch, local businesses have been excited to obtain fast, affordable, reliable connectivity.

The full RFP is available on the city's website.

Yellow Springs, OH, Releases RFP: Proposals Due August 22

Earlier this year, the grassroots group, Springs-Net, presented its white paper on a potential municipal network in their town of 3,700 people. The village, located in central Ohio between Dayton and Columbus, is taking up the suggestion and recently released a Request for Proposals (RFP) for a broadband needs assessment and business plan.

The village already operates municipal electric, water, sewer, and storm water utilities, however does not own any municipal fiber. According to the RFP, Yellow Springs collaborates with several local schools and an educational computer association for connectivity to the village’s municipal office location. There is also fiber in the community owned by the Ohio Academic Research Network (OARNet) and a non-profit datacenter in the area.

Yellow Springs wants interested firms to answer their call and provide options for:

  • Mapping Needs Assessment
  • Business and Financial Model
  • Governance and Ownership Strategy
  • Funding and Financial Analysis
  • Public-Private Partnership Development
  • Infrastructure Recommendations

There will be an informal session for respondents on August 1 at 11 a.m. in the Yellow Springs Council Chambers and proposals are due on August 22, 2016. Check out the Yellow Springs website for more details on the RFP.

Yellow Springs, OH, Releases RFP: Proposals Due August 22

Earlier this year, the grassroots group, Springs-Net, presented its white paper on a potential municipal network in their town of 3,700 people. The village, located in central Ohio between Dayton and Columbus, is taking up the suggestion and recently released a Request for Proposals (RFP) for a broadband needs assessment and business plan.

The village already operates municipal electric, water, sewer, and storm water utilities, however does not own any municipal fiber. According to the RFP, Yellow Springs collaborates with several local schools and an educational computer association for connectivity to the village’s municipal office location. There is also fiber in the community owned by the Ohio Academic Research Network (OARNet) and a non-profit datacenter in the area.

Yellow Springs wants interested firms to answer their call and provide options for:

  • Mapping Needs Assessment
  • Business and Financial Model
  • Governance and Ownership Strategy
  • Funding and Financial Analysis
  • Public-Private Partnership Development
  • Infrastructure Recommendations

There will be an informal session for respondents on August 1 at 11 a.m. in the Yellow Springs Council Chambers and proposals are due on August 22, 2016. Check out the Yellow Springs website for more details on the RFP.

Yellow Springs, OH, Releases RFP: Proposals Due August 22

Earlier this year, the grassroots group, Springs-Net, presented its white paper on a potential municipal network in their town of 3,700 people. The village, located in central Ohio between Dayton and Columbus, is taking up the suggestion and recently released a Request for Proposals (RFP) for a broadband needs assessment and business plan.

The village already operates municipal electric, water, sewer, and storm water utilities, however does not own any municipal fiber. According to the RFP, Yellow Springs collaborates with several local schools and an educational computer association for connectivity to the village’s municipal office location. There is also fiber in the community owned by the Ohio Academic Research Network (OARNet) and a non-profit datacenter in the area.

Yellow Springs wants interested firms to answer their call and provide options for:

  • Mapping Needs Assessment
  • Business and Financial Model
  • Governance and Ownership Strategy
  • Funding and Financial Analysis
  • Public-Private Partnership Development
  • Infrastructure Recommendations

There will be an informal session for respondents on August 1 at 11 a.m. in the Yellow Springs Council Chambers and proposals are due on August 22, 2016. Check out the Yellow Springs website for more details on the RFP.

Yellow Springs, OH, Releases RFP: Proposals Due August 22

Earlier this year, the grassroots group, Springs-Net, presented its white paper on a potential municipal network in their town of 3,700 people. The village, located in central Ohio between Dayton and Columbus, is taking up the suggestion and recently released a Request for Proposals (RFP) for a broadband needs assessment and business plan.

The village already operates municipal electric, water, sewer, and storm water utilities, however does not own any municipal fiber. According to the RFP, Yellow Springs collaborates with several local schools and an educational computer association for connectivity to the village’s municipal office location. There is also fiber in the community owned by the Ohio Academic Research Network (OARNet) and a non-profit datacenter in the area.

Yellow Springs wants interested firms to answer their call and provide options for:

  • Mapping Needs Assessment
  • Business and Financial Model
  • Governance and Ownership Strategy
  • Funding and Financial Analysis
  • Public-Private Partnership Development
  • Infrastructure Recommendations

There will be an informal session for respondents on August 1 at 11 a.m. in the Yellow Springs Council Chambers and proposals are due on August 22, 2016. Check out the Yellow Springs website for more details on the RFP.

Yellow Springs, OH, Releases RFP: Proposals Due August 22

Earlier this year, the grassroots group, Springs-Net, presented its white paper on a potential municipal network in their town of 3,700 people. The village, located in central Ohio between Dayton and Columbus, is taking up the suggestion and recently released a Request for Proposals (RFP) for a broadband needs assessment and business plan.

The village already operates municipal electric, water, sewer, and storm water utilities, however does not own any municipal fiber. According to the RFP, Yellow Springs collaborates with several local schools and an educational computer association for connectivity to the village’s municipal office location. There is also fiber in the community owned by the Ohio Academic Research Network (OARNet) and a non-profit datacenter in the area.

Yellow Springs wants interested firms to answer their call and provide options for:

  • Mapping Needs Assessment
  • Business and Financial Model
  • Governance and Ownership Strategy
  • Funding and Financial Analysis
  • Public-Private Partnership Development
  • Infrastructure Recommendations

There will be an informal session for respondents on August 1 at 11 a.m. in the Yellow Springs Council Chambers and proposals are due on August 22, 2016. Check out the Yellow Springs website for more details on the RFP.

Leverett Releases RFP For ISP: Responses Due August 15th

Leverett, Massachusetts, has operated its Fiber-to-the-Home (FTTH) network since August 2015, working with Crocker Communications to bring Gigabit per second (Gbps) connectivity to residents and businesses in the Massachusetts town. The contract with Crocker is not indefinite, however, and the city has issued a Request for Proposals (RFP) for other Internet Service Providers (ISPs) to offer services on the network. Responses are due August 15, 2016.

According to the RFP, the ISP selected will have an exclusive agreement to provide services to the community as leverettnet.net. The community seeks a three-year contract and will begin on or before July 1, 2017. 

Leverett’s contract with Crocker Communications was also a three-year term, commencing in 2014. Releasing an RFP now will give community leaders eleven months to review submissions from potential providers and negotiate terms. With their own infrastructure, Leverett has the ability to take a discerning approach and explore other options from the RFP release.

RFP SCHEDULE: 

Written Questions Due: July 18, 2016 at 10 a.m. 

Answers to Questions Posted: July 25, 2016

Submission of Proposals Due: August 15, 2016 at 10 a.m.

Finalist Named: August 26th, 2016

Contract Award: September 2nd, 2016

Leverett Releases RFP For ISP: Responses Due August 15th

Leverett, Massachusetts, has operated its Fiber-to-the-Home (FTTH) network since August 2015, working with Crocker Communications to bring Gigabit per second (Gbps) connectivity to residents and businesses in the Massachusetts town. The contract with Crocker is not indefinite, however, and the city has issued a Request for Proposals (RFP) for other Internet Service Providers (ISPs) to offer services on the network. Responses are due August 15, 2016.

According to the RFP, the ISP selected will have an exclusive agreement to provide services to the community as leverettnet.net. The community seeks a three-year contract and will begin on or before July 1, 2017. 

Leverett’s contract with Crocker Communications was also a three-year term, commencing in 2014. Releasing an RFP now will give community leaders eleven months to review submissions from potential providers and negotiate terms. With their own infrastructure, Leverett has the ability to take a discerning approach and explore other options from the RFP release.

RFP SCHEDULE: 

Written Questions Due: July 18, 2016 at 10 a.m. 

Answers to Questions Posted: July 25, 2016

Submission of Proposals Due: August 15, 2016 at 10 a.m.

Finalist Named: August 26th, 2016

Contract Award: September 2nd, 2016

Leverett Releases RFP For ISP: Responses Due August 15th

Leverett, Massachusetts, has operated its Fiber-to-the-Home (FTTH) network since August 2015, working with Crocker Communications to bring Gigabit per second (Gbps) connectivity to residents and businesses in the Massachusetts town. The contract with Crocker is not indefinite, however, and the city has issued a Request for Proposals (RFP) for other Internet Service Providers (ISPs) to offer services on the network. Responses are due August 15, 2016.

According to the RFP, the ISP selected will have an exclusive agreement to provide services to the community as leverettnet.net. The community seeks a three-year contract and will begin on or before July 1, 2017. 

Leverett’s contract with Crocker Communications was also a three-year term, commencing in 2014. Releasing an RFP now will give community leaders eleven months to review submissions from potential providers and negotiate terms. With their own infrastructure, Leverett has the ability to take a discerning approach and explore other options from the RFP release.

RFP SCHEDULE: 

Written Questions Due: July 18, 2016 at 10 a.m. 

Answers to Questions Posted: July 25, 2016

Submission of Proposals Due: August 15, 2016 at 10 a.m.

Finalist Named: August 26th, 2016

Contract Award: September 2nd, 2016